Rosário Oliveira / Procedia Structural Integrity 22 (2019) 151–159 Rosário Oliveira / Structural Integrity Procedia 00 (2019) 000 – 000
155
5
As the Budget At Completion (BAC) is the total amount budgeted in the baseline, the Estimate At Completion (EAC = AC + (BAC-EV) / CPI) gives the value of the final cost of the works, if the performance time and costs recorded in the status date are maintained. Thus, at the state date, if EAC> BAC, then the work at completion will have a higher cost if the work performance in the work remains the same as the identified; if EAC